Project schedule constraints include resource
constraints, finance and supply constraints, calendar
constraints and imposed dates. The critical path in the
projects with imposed dates and different activity and
resource calendars can consist of only one final
activity. Managing project schedules, one should pay
more attention to activity floats. The activities with
shorter floats are more critical than the activities
with longer floats. pdf